The North Wales Wind Farms Connection Order 2016

17 August 2016

This Order authorises SP Manweb PLC (referred to in this Order as the undertaker) to install and keep installed, use and maintain, a 132 kV electric line above ground, approximately 17.4 km in length.

What is the primary legislation that provides these powers: Section 114 and 120 of the Planning Act 2008
These Regulations amend the: n/a
Who does this affect: England and Wales
When does this change take place: 19th August 2016

The Secretary of State, having decided the application, has determined to make an order giving effect to the proposals comprised in the application on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.